Bridge Type
Main Span(s): Prestressed concrete [5] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 109.7 m = 359.9 ft
Main Spans: 2 at 71 m = 233.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 9.1 m = 29.9 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Whatcom County [073], Washington [53]
Owned by County Highway Agency [02], DOT District: 1
0.3 W HWY 9
Condition
Deck: Very Good [8]
Superstructure: Very Good [8]
Substructure: Very Good [8]
Loading
Design: HL93 [A]
Operating: 53.8 metric ton = 59.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 41.5 metric ton = 45.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present desirable criteria [8]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: October 1999 [1099] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 15.9 km = 9.9 mi
Traffic
ADT: 557 (2017) and Trucks: 11%
Future ADT: 870 (In 2039
)