Bridge Type
Main Span(s): Concrete continuous [2] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 241.1 m = 791.0 ft
Main Spans: 15 at 24.1 m = 79.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 13.4 m = 44.0 ft (2 Lanes) and Out-To-Out: 14.3 m = 46.9 ft for a 13.4 m = 44.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Jennings [38355]: Jefferson Davis Parish [053], Louisiana [22]
Owned by State Highway Agency [01], DOT District: 7
4.3 MI EAST OF LA 395
Condition
Deck: Very Good [8]
Superstructure: Very Good [8]
Substructure: Very Good [8]
Loading
Design: MS 18 / HS 20 [5]
Operating: 61.7 metric ton = 67.9 tons (Load Factor(LF) [1])
Inventory: 32.7 metric ton = 36.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present desirable criteria [8]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 4900 (2016) and Trucks: 10%
Future ADT: 3000 (In 2036
)