Bridge Type
Main Span(s): Concrete [1] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface:
Bridge Dimensions
Length: 54.9 m = 180.1 ft
Main Spans: 5 at 11 m = 36.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 10.2 m = 33.5 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Saraland [68160]: Mobile County [097], Alabama [01]
Owned by State Highway Agency [01], DOT District: 9
JCT SR 213
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: M 18 / H 20 [4]
Operating: 40.7 metric ton = 44.8 tons (Load Factor(LF) [1])
Inventory: 24.4 metric ton = 26.8 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 11625 (2018) and Trucks: 7%
Future ADT: 17438 (In 2038
)