Bridge Type
Main Span(s): Concrete [1] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface:
Bridge Dimensions
Length: 24.1 m = 79.1 ft
Main Spans: 4 at 6.1 m = 20.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.3 m = 24.0 ft (2 Lanes) and Out-To-Out: 8.1 m = 26.6 ft for a 7.9 m = 25.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Ouachita Parish [073], Louisiana [22]
Owned by County Highway Agency [02], DOT District: 5
1.0 MI SE of LA 546
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 51.8 metric ton = 57.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 40.2 metric ton = 44.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 15.9 km = 9.9 mi
Traffic
ADT: 350 (2004) and Trucks: 0%
Future ADT: 210 (In 2036
)