Bridge Type
Main Span(s): Steel continuous [4] Girder and floorbeam system [03]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface:
Bridge Dimensions
Length: 246.3 m = 808.1 ft
Main Spans: 3 at 79.2 m = 259.9 ft
Approach Spans: 2
Skew: 0
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 13 m = 42.7 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 14.9 m = 48.9 ft
Location
Unknown [00000]: Walker County [127], Alabama [01]
Owned by State Highway Agency [01], DOT District: 10
6 MI E JASPER
Condition
Deck: Satisfactory [6]
Superstructure: Poor [4]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 36.7 metric ton = 40.4 tons (Load Factor(LF) [1])
Inventory: 21.9 metric ton = 24.1 tons (Load Factor(LF) [1])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: May 2020 [0520] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 5330 (2013) and Trucks: 18%
Future ADT: 6673 (In 2040
)