Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Steel plate (includes orthotropic) [5] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 23.2 m = 76.1 ft
Main Spans: 3 at 7.6 m = 24.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 2.8 m = 9.2 ft (1 Lanes) and Out-To-Out: 2.9 m = 9.5 ft for a 3 m = 9.8 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Monterey County [053], California [06]
Owned by County Highway Agency [02], DOT District: 5
2.6 ME E OF RTE 25
Condition
Deck: Good [7]
Superstructure: Fair [5]
Substructure: Good [7]
Loading
Design: M 13.5 / H 15 [2]
Operating: 52.8 metric ton = 58.1 tons (Load Factor(LF) [1])
Inventory: 31.8 metric ton = 35.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Meets minimum tolerable limits to be left in place as is [4]
Waterway: Somewhat better than minimum adequacy to tolerate being left in place as is [5] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: August 1999 [899] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 19.9 km = 12.3 mi
Traffic
ADT: 150 (2013) and Trucks: 3%
Future ADT: 316 (In 2041
)