HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 11


WOLF CREEK HWY over WOLF CREEK (Route: 61)
Num:24079x
Open: no restriction [A]
Built: 1986, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.1 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Epoxy Overlay [5]
Bridge Dimensions
Length: 52.4 m = 171.9 ft
Main Spans: 2 at 26.2 m = 86.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 10.5 m = 34.5 ft (2 Lanes) and Out-To-Out: 11.5 m = 37.7 ft for a 6.7 m = 22.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
0.2 FR 678W 3.31 FR 650
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 73.5 metric ton = 80.9 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 56.2 metric ton = 61.8 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.5 km = 0.3 mi
Traffic
ADT: 406 (2018) and Trucks: 5%
Future ADT: 609 (In 2040 )
North Scenic Hwy. over LAUREL FORK @ ROCKY GAP (Route: 52)
Num:2959x
Open: no restriction [A]
Built: 1927, Reconstructed: 1992
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface:
Bridge Dimensions
Length: 25.9 m = 85.0 ft
Main Spans: 2 at 13.1 m = 43.0 ft
Approach Spans: 0
Skew: 30
Width, Roadway: 7.3 m = 24.0 ft (2 Lanes) and Out-To-Out: 8.5 m = 27.9 ft for a 6.4 m = 21.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
.02 FR 61 S - .03 TO 61 N
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 65.3 metric ton = 71.8 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 50.8 metric ton = 55.9 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 1.3 km = 0.8 mi
Traffic
ADT: 532 (2018) and Trucks: 7%
Future ADT: 798 (In 2040 )
QUARRY DRIVE over CLEAR FORK CREEK (Route: 665)
Num:3123x
Open: no restriction [A]
Built: 1927, Reconstructed: 1989
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 34.4 m = 112.9 ft
Main Spans: 3 at 11.6 m = 38.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.1 m = 23.3 ft (2 Lanes) and Out-To-Out: 8 m = 26.2 ft for a 6.1 m = 20.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
.07 FR 61-.39 TO END MAIN
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: M 13.5 / H 15 [2]
Operating: 32.7 metric ton = 36.0 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 24.5 metric ton = 27.0 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 15.9 km = 9.9 mi
Traffic
ADT: 208 (2015) and Trucks: 0%
Future ADT: 312 (In 2035 )
I-77 NBL RAMP D over CLEAR FORK CREEK (Route: 77)
Num:3022x
Open: no restriction [A]
Built: 1974, Reconstructed: 1992
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 61.9 m = 203.1 ft
Main Spans: 3 at 25.3 m = 83.0 ft
Approach Spans: 0
Skew: 14
Width, Roadway: 9.4 m = 30.8 ft (2 Lanes) and Out-To-Out: 10.6 m = 34.8 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
0.05TO61; 18.28 WYTHE CO
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 51.7 metric ton = 56.9 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 39.9 metric ton = 43.9 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: January 2021 [0121] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 760 (2019) and Trucks: 7%
Future ADT: 1140 (In 2039 )
Rte 665 over WOLF CREEK (Route: 665)
Num:29589x
Open: no restriction [A]
Built: 2011, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface:
Bridge Dimensions
Length: 64 m = 210.0 ft
Main Spans: 2 at 32 m = 105.0 ft
Approach Spans: 0
Skew: 30
Width, Roadway: 6.6 m = 21.7 ft (2 Lanes) and Out-To-Out: 7.4 m = 24.3 ft for a 6.4 m = 21.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
0.25 TO 630-0.25 DEAD END
Condition
Deck: Satisfactory [6]
Superstructure: Very Good [8]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 58.1 metric ton = 63.9 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 44.5 metric ton = 49.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Meets minimum tolerable limits to be left in place as is [4]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: June 1999 [699] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 15.9 km = 9.9 mi
Traffic
ADT: 208 (2015) and Trucks: 0%
Future ADT: 256 (In 2039 )
I-77 NBL over CLEAR FORK CREEK (Route: 77)
Num:2993x
Open: no restriction [A]
Built: 1974, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 73.2 m = 240.2 ft
Main Spans: 3 at 26 m = 85.3 ft
Approach Spans: 0
Skew: 20
Width, Roadway: 12 m = 39.4 ft (2 Lanes) and Out-To-Out: 13.2 m = 43.3 ft for a 15.8 m = 51.8 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
5.73 FT 52S; 2.18 TO 52N
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 65.3 metric ton = 71.8 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 50.8 metric ton = 55.9 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: March 1999 [399] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 13556 (2018) and Trucks: 28%
Future ADT: 24000 (In 2038 )
I-77 SBL over CLEAR FORK CREEK (Route: 77)
Num:2992x
Open: no restriction [A]
Built: 1974, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 73.2 m = 240.2 ft
Main Spans: 3 at 25.9 m = 85.0 ft
Approach Spans: 0
Skew: 20
Width, Roadway: 12 m = 39.4 ft (2 Lanes) and Out-To-Out: 13.3 m = 43.6 ft for a 15.8 m = 51.8 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
5.73 FR 52S; 2.18 TO 52N
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 65.3 metric ton = 71.8 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 50.8 metric ton = 55.9 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: March 1999 [399] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 14618 (2018) and Trucks: 28%
Future ADT: 20640 (In 2038 )
I-77 SBL RAMP A over CLEAR FORK CREEK (Route: 77)
Num:3023x
Open: no restriction [A]
Built: 1974, Reconstructed: 1992
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 92.7 m = 304.1 ft
Main Spans: 4 at 27.7 m = 90.9 ft
Approach Spans: 0
Skew: 28
Width, Roadway: 8.3 m = 27.2 ft (2 Lanes) and Out-To-Out: 9.5 m = 31.2 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
16.31 WYTHE CO; 0.05TO 61
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 68 metric ton = 74.8 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 52.6 metric ton = 57.9 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: January 2021 [0121] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 1100 (2019) and Trucks: 3%
Future ADT: 1375 (In 2039 )
INTERSTATE 77 NBL over RTES 52 & 61 (Route: 77)
Num:2996x
Open: no restriction [A]
Built: 1974, Reconstructed: 1991
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 76.8 m = 252.0 ft
Main Spans: 4 at 21.6 m = 70.9 ft
Approach Spans: 0
Skew: 40
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 13.4 m = 44.0 ft for a 15.8 m = 51.8 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
058452 S 020752 N
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 85.3 metric ton = 93.8 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 66.2 metric ton = 72.8 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: November 1999 [1199] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 15000 (2018) and Trucks: 28%
Future ADT: 2250 (In 2039 )
SBL RTE 0077 over RTES 52 & 61 (Route: 77)
Num:2994x
Open: no restriction [A]
Built: 1974, Reconstructed: 1991
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 76.8 m = 252.0 ft
Main Spans: 4 at 22.4 m = 73.5 ft
Approach Spans: 0
Skew: 40
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 13.4 m = 44.0 ft for a 15.8 m = 51.8 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
058452 S 020752 N
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 72.6 metric ton = 79.9 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 56.2 metric ton = 61.8 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: November 1999 [1199] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 14000 (2018) and Trucks: 27%
Future ADT: 21000 (In 2039 )
US52(N.SCENIC HWY) over CLEAR FORK CREEK (Route: 52)
Num:2966x
Open: no restriction [A]
Built: 1974, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.5 Miles (0.8 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 35.6 m = 116.8 ft
Main Spans: 2 at 17.7 m = 58.1 ft
Approach Spans: 0
Skew: 20
Width, Roadway: 7.8 m = 25.6 ft (2 Lanes) and Out-To-Out: 9 m = 29.5 ft for a 6.4 m = 21.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Bland County [021], Virginia [51]
Owned by State Highway Agency [01], DOT District: 1
0.0 FR 61 - 2.00 TO 606
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 56.2 metric ton = 61.8 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 43.5 metric ton = 47.9 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 532 (2018) and Trucks: 7%
Future ADT: 798 (In 2040 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact

Divider