Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface:
Bridge Dimensions
Length: 27.9 m = 91.5 ft
Main Spans: 3 at 12.2 m = 40.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.4 m = 24.3 ft (2 Lanes) and Out-To-Out: 7.4 m = 24.3 ft for a 5.8 m = 19.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Pope County [151], Illinois [17]
Owned by Town or Township Highway Agency [03], DOT District: 9
2 MI W HOMBERG
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Poor [4]
Loading
Design: MS 18 / HS 20 [5]
Operating: 61.6 metric ton = 67.8 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 36.9 metric ton = 40.6 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: September 1999 [999] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 1.6 km = 1.0 mi
Traffic
ADT: 50 (2018) and Trucks: 10%
Future ADT: 80 (In 2032
)