HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 4


23RD STREET over CALTRAIN (Route: 0)
Num: 34C0091x
Open: no restriction [A]
Built: 2016, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 31.7 m = 104.0 ft
Main Spans: 2 at 17.6 m = 57.7 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 12.8 m = 42.0 ft (2 Lanes) and Out-To-Out: 20.2 m = 66.3 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
San Francisco [67000]: San Francisco County [075], California [06]
Owned by Other Local Agencies [25], DOT District: 4
JEO PENNSYLVANIA AVE
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 54.1 metric ton = 59.5 tons ()
Inventory: 32.4 metric ton = 35.6 tons ()
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: December 2018 [1218] and Frequency: 48
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 8000 (2013) and Trucks: 5%
Future ADT: 10202 (In 2040 )
22ND STREET over CALTRAIN (Route: 0)
Num: 34C0092x
Open: no restriction [A]
Built: 2016, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface:
Bridge Dimensions
Length: 32.6 m = 107.0 ft
Main Spans: 2 at 18.3 m = 60.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 12.8 m = 42.0 ft (2 Lanes) and Out-To-Out: 20.2 m = 66.3 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 8.2 m = 26.9 ft and Navigational Clearance: 0 = N/A
Location
San Francisco [67000]: San Francisco County [075], California [06]
Owned by Other Local Agencies [25], DOT District: 4
JEO PENNSYLVANIA AVE
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 54 metric ton = 59.4 tons ()
Inventory: 32.4 metric ton = 35.6 tons ()
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: December 2020 [1220] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 8000 (2013) and Trucks: 5%
Future ADT: 10000 (In 2040 )
EVANS AVE over CALTRAIN & UP RR (Route: 0)
Num: 34C0054x
Open: no restriction [A]
Built: 1947, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 32.3 m = 106.0 ft
Main Spans: 3 at 16.5 m = 54.1 ft
Approach Spans: 0
Skew: 2
Width, Roadway: 19.5 m = 64.0 ft (4 Lanes) and Out-To-Out: 24.4 m = 80.1 ft for a 19.5 m = 64.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
San Francisco [67000]: San Francisco County [075], California [06]
Owned by County Highway Agency [02], DOT District: 4
JUST S. OF CESAR CHAVEZ
Condition
Deck: Fair [5]
Superstructure: Good [7]
Substructure: Fair [5]
Loading
Design:
Operating: 28.5 metric ton = 31.4 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 19.4 metric ton = 21.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: December 1999 [1299] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 30000 (2016) and Trucks: 10%
Future ADT: 50000 (In 2036 )
20TH STREET over ROUTE 280 (Route: 0)
Num: 34 0098x
Open: no restriction [A]
Built: 1968, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.7 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface:
Bridge Dimensions
Length: 240.8 m = 790.1 ft
Main Spans: 10 at 27.4 m = 89.9 ft
Approach Spans: 0
Skew: 4
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 11.5 m = 37.7 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
San Francisco [67000]: San Francisco County [075], California [06]
Owned by State Highway Agency [01], DOT District: 4
04-SF-280-R6.39-SF
Condition
Deck: Fair [5]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 35.6 metric ton = 39.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 27.5 metric ton = 30.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 2700 (2017) and Trucks: 1%
Future ADT: 5222 (In 2040 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact