Main Span(s): Prestressed concrete continuous [6] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 34.3 m = 112.5 ft
Main Spans: 3 at 13.1 m = 43.0 ft
Approach Spans: 0
Skew: 15
Width, Roadway: 7.4 m = 24.3 ft (2 Lanes) and Out-To-Out: 8.1 m = 26.6 ft for a 5.8 m = 19.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Ripley County [137], Indiana [18]
Owned by County Highway Agency [02], DOT District: 5
00.22 W OF CR 200 W
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 69.8 metric ton = 76.8 tons (Load Factor(LF) [1])
Inventory: 41.7 metric ton = 45.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 150 (2018) and Trucks: 4%