Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 106.1 m = 348.1 ft
Main Spans: 2 at 28.7 m = 94.2 ft
Approach Spans: 2
Skew: 18
Width, Roadway: 7.9 m = 25.9 ft (2 Lanes) and Out-To-Out: 10.4 m = 34.1 ft for a 10.7 m = 35.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Fairmont [26452]: Marion County [049], West Virginia [54]
Owned by City or Municipal Highway Agency [04], DOT District: 4
0.23 MI NORTH WV RT 310
Condition
Deck: Poor [4]
Superstructure: Poor [4]
Substructure: Fair [5]
Loading
Design: MS 13.5 / HS 15 [3]
Operating: 27.2 metric ton = 29.9 tons (Load Factor(LF) [1])
Inventory: 16.3 metric ton = 17.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: September 1999 [999] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 2000 (2019) and Trucks: 9%
Future ADT: 2500 (In 2039
)