Bridge Type
Main Span(s): Concrete continuous [2] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 56.1 m = 184.1 ft
Main Spans: 4 at 15.2 m = 49.9 ft
Approach Spans: 0
Skew: 15
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 9.8 m = 32.2 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Camden [11024]: Preble County [135], Ohio [39]
Owned by State Highway Agency [01], DOT District: 8
CAMDEN EAST CORP. LINE
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: M 13.5 / H 15 [2]
Operating: 48.6 metric ton = 53.5 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 29.2 metric ton = 32.1 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: August 2020 [0820] and Frequency: 12
Future Work
Work Needed:
Bridge Detour: 2.4 km = 1.5 mi
Traffic
ADT: 3809 (2015) and Trucks: 7%
Future ADT: 5287 (In 2038
)