Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 29.6 m = 97.1 ft
Main Spans: 1 at 28 m = 91.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 11.6 m = 38.1 ft (2 Lanes) and Out-To-Out: 12.5 m = 41.0 ft for a 11.6 m = 38.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Thurmont [77825]: Frederick County [021], Maryland [24]
Owned by County Highway Agency [02], DOT District: 7
0.5 M N OF EYLER ROAD
Condition
Deck: Satisfactory [6]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 99.9 metric ton = 109.9 tons (Load Factor(LF) [1])
Inventory: 59.9 metric ton = 65.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: October 1999 [1099] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 1355 (2016) and Trucks: 8%
Future ADT: 2450 (In 2036
)