Bridge Type
Main Span(s): Prestressed concrete continuous [6] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 54.6 m = 179.1 ft
Main Spans: 3 at 17.5 m = 57.4 ft
Approach Spans: 0
Skew: 30
Width, Roadway: 13.8 m = 45.3 ft (2 Lanes) and Out-To-Out: 14.8 m = 48.6 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Parke County [121], Indiana [18]
Owned by State Highway Agency [01], DOT District: 1
03.35 W SR 59
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 59 metric ton = 64.9 tons (Load Factor(LF) [1])
Inventory: 35.4 metric ton = 38.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: March 2020 [0320] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 2.4 km = 1.5 mi
Traffic
ADT: 5130 (2006) and Trucks: 10%
Future ADT: 7105 (In 2034
)