Bridge Type
Main Span(s): Concrete [1] Arch - Deck [11]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 79.2 m = 259.9 ft
Main Spans: 3 at 27.3 m = 89.6 ft
Approach Spans: 0
Skew: 17
Width, Roadway: 18.2 m = 59.7 ft (6 Lanes) and Out-To-Out: 25.6 m = 84.0 ft for a 14.6 m = 47.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Indianapolis [36000]: Marion County [097], Indiana [18]
Owned by City or Municipal Highway Agency [04], DOT District: 3
00.30 S OF 30TH ST
Condition
Deck: Not Applicable [N]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: Other [C]
Operating: 32.7 metric ton = 36.0 tons ()
Inventory: 32.7 metric ton = 36.0 tons ()
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4]
Inspections
Date: August 2020 [0820] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 8709 (2019) and Trucks: 5%
Future ADT: 12940 (In 2039
)