HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 3


WOODLAWN ST(FAU 73 over TEN MILE CREEK (Route: 0)
Num:20600100000000x
Open: no restriction [A]
Built: 1963, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.1 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface:
Bridge Dimensions
Length: 20.7 m = 67.9 ft
Main Spans: 2 at 10.1 m = 33.1 ft
Approach Spans: 0
Skew: 35
Width, Roadway: 7.3 m = 24.0 ft (2 Lanes) and Out-To-Out: 9.6 m = 31.5 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [01145]: De Witt County [039], Illinois [17]
Owned by City or Municipal Highway Agency [04], DOT District: 5
CITY OF CLINTON
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: M 13.5 / H 15 [2]
Operating: 53.8 metric ton = 59.2 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 32.4 metric ton = 35.6 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: December 2020 [1220] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 175 (2018) and Trucks: 17%
Future ADT: 200 (In 2032 )
FAU-7331 (Walnut S over Ten Mile Creek (Route: 0)
Num:20310000000000x
Open: no restriction [A]
Built: 1974, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Channel beam [22]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface:
Bridge Dimensions
Length: 33.3 m = 109.3 ft
Main Spans: 3 at 10.7 m = 35.1 ft
Approach Spans: 0
Skew: 30
Width, Roadway: 7.9 m = 25.9 ft (2 Lanes) and Out-To-Out: 8 m = 26.2 ft for a 7.3 m = 24.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [01145]: De Witt County [039], Illinois [17]
Owned by City or Municipal Highway Agency [04], DOT District: 5
NW EDGE CLINTON
Condition
Deck: Poor [4]
Superstructure: Poor [4]
Substructure: Satisfactory [6]
Loading
Design: MS 13.5 / HS 15 [3]
Operating: 48.9 metric ton = 53.8 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 29.5 metric ton = 32.5 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Somewhat better than minimum adequacy to tolerate being left in place as is [5] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: December 2020 [1220] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.5 km = 0.3 mi
Traffic
ADT: 500 (2018) and Trucks: 4%
Future ADT: 500 (In 2032 )
CRESTVIEW ST (1010 over TEN MILE CREEK (Route: 0)
Num:20310900000000x
Open: no restriction [A]
Built: 1977, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface:
Bridge Dimensions
Length: 37.5 m = 123.0 ft
Main Spans: 3 at 12.5 m = 41.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.3 m = 24.0 ft (2 Lanes) and Out-To-Out: 7.3 m = 24.0 ft for a 7.3 m = 24.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [01145]: De Witt County [039], Illinois [17]
Owned by City or Municipal Highway Agency [04], DOT District: 5
CITY OF CLINTON
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 44.4 metric ton = 48.8 tons (Unknown [D])
Inventory: 32.4 metric ton = 35.6 tons (Unknown [D])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: February 1999 [299] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.6 km = 0.4 mi
Traffic
ADT: 75 (2018) and Trucks: 7%
Future ADT: 75 (In 2032 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact

Divider