Bridge Type
Main Span(s): Concrete [1] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 19.5 m = 64.0 ft
Main Spans: 1 at 18.6 m = 61.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.1 m = 23.3 ft (1 Lanes) and Out-To-Out: 7.9 m = 25.9 ft for a 6.4 m = 21.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Smithfield [72767]: Jefferson County [081], Ohio [39]
Owned by County Highway Agency [02], DOT District: 11
0.2 miles E of CR12
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: HL93 [A]
Operating: 42.1 metric ton = 46.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 25.9 metric ton = 28.5 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Basically intolerable requiring high priority of corrrective action [3] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: April 2020 [0420] and Frequency: 12
Future Work
Work Needed:
Bridge Detour: 0.6 km = 0.4 mi
Traffic
ADT: 203 (2015) and Trucks: 7%
Future ADT: 282 (In 2038
)