HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 4


MCGUINNESS BLVD over 11TH STREET: 50TH AVENUE (Route: 0)
Num:2240639x
Open: no restriction [A]
Built: 1954, Reconstructed: 1993
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Steel [3] Movable - Bascule [16]
Approach Span(s): Steel [3] Girder and floorbeam system [03]
Deck: Not applicable [N] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 734.9 m = 2411.2 ft
Main Spans: 1 at 52.7 m = 172.9 ft
Approach Spans: 43
Skew: 0
Width, Roadway: 21.1 m = 69.2 ft (6 Lanes) and Out-To-Out: 26.1 m = 85.6 ft for a 21 m = 68.9 ft approaching roadway.
Vertical Clearance: 4.37 m = 14.3 ft and Navigational Clearance: 0 = N/A
Location
New York [51000]: Kings County [047], New York [36]
Owned by City or Municipal Highway Agency [04], DOT District: 0
OVER NEWTOWN CREEK
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 53.5 metric ton = 58.9 tons (Allowable Stress(AS) [2])
Inventory: 32.7 metric ton = 36.0 tons (Allowable Stress(AS) [2])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Somewhat better than minimum adequacy to tolerate being left in place as is [5] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: May 2020 [0520] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0.4 km = 0.2 mi
Traffic
ADT: 36553 (2019) and Trucks: 8%
Future ADT: 36724 (In 2039 )
JACKSON AVENUE over LONG ISLAND RR (Route: 0)
Num:2247260x
Open: no restriction [A]
Built: 1896, Reconstructed: 1987
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 9.1 m = 29.9 ft
Main Spans: 1 at 8.2 m = 26.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 39.3 m = 128.9 ft (4 Lanes) and Out-To-Out: 47.9 m = 157.2 ft for a 39.3 m = 128.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
New York [51000]: Queens County [081], New York [36]
Owned by City or Municipal Highway Agency [04], DOT District: 0
AT LONG ISLAND CITY
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 78.4 metric ton = 86.2 tons ()
Inventory: 32.7 metric ton = 36.0 tons ()
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: August 2020 [0820] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 21708 (2019) and Trucks: 8%
Future ADT: 21810 (In 2039 )
RTE 25 over LIRR-N SHORE YARD (Route: 25)
Num:2247270x
Open: no restriction [A]
Built: 1908, Reconstructed: 1993
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 83.5 m = 274.0 ft
Main Spans: 6 at 17 m = 55.8 ft
Approach Spans: 0
Skew: 21
Width, Roadway: 12.8 m = 42.0 ft (2 Lanes) and Out-To-Out: 19.6 m = 64.3 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
New York [51000]: Queens County [081], New York [36]
Owned by City or Municipal Highway Agency [04], DOT District: 0
AT HUNTERS POINT
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 35.4 metric ton = 38.9 tons (Load Factor(LF) [1])
Inventory: 20.9 metric ton = 23.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: November 1999 [1199] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 8876 (2018) and Trucks: 16%
Future ADT: 10782 (In 2039 )
49TH AVENUE over LONG ISLAND RR: AMTRAK (Route: 0)
Num:2247290x
Open: no restriction [A]
Built: 1908, Reconstructed: 1983
Historic: Bridge is eligible for the NRHP. [2]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel [3] Girder and floorbeam system [03]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 101.2 m = 332.0 ft
Main Spans: 5 at 22.3 m = 73.2 ft
Approach Spans: 0
Skew: 54
Width, Roadway: 12.8 m = 42.0 ft (4 Lanes) and Out-To-Out: 19 m = 62.3 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
New York [51000]: Queens County [081], New York [36]
Owned by City or Municipal Highway Agency [04], DOT District: 0
AT SUNNYSIDE
Condition
Deck: Fair [5]
Superstructure: Poor [4]
Substructure: Fair [5]
Loading
Design:
Operating: 55.3 metric ton = 60.8 tons (Load Factor(LF) [1])
Inventory: 32.7 metric ton = 36.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 13434 (2016) and Trucks: 8%
Future ADT: 26361 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.