Bridge Type
Main Span(s): Concrete [1] Culvert [19]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Not applicable (applies only to structures with no deck) [N]
Bridge Dimensions
Length: 19.8 m = 65.0 ft
Main Spans: 1 at 19.8 m = 65.0 ft
Approach Spans: 0
Skew: 10
Width, Roadway: 9.8 m = 32.2 ft (2 Lanes) and Out-To-Out: 10.8 m = 35.4 ft for a 7.6 m = 24.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Peru [59328]: Miami County [103], Indiana [18]
Owned by County Highway Agency [02], DOT District: 2
00.80 N of CR 225 S
Condition
Deck: Not Applicable [N]
Superstructure: Not Applicable [N]
Substructure: Not Applicable [N]
Loading
Design: M 18 / H 20 [4]
Operating: 62.6 metric ton = 68.9 tons (Load Factor(LF) [1])
Inventory: 37.2 metric ton = 40.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: May 1999 [599] and Frequency: 24
Future Work
Work Needed: Other structural work: including hydraulic replacements. [38]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 12525 (2011) and Trucks: 5%
Future ADT: 21000 (In 2031
)