HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 3


E WATSON ST over TRIB TO VERMILLION C (Route: 0)
Num:53680300000000x
Open: no restriction [A]
Built: 2003, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Culvert [19]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 9.2 m = 30.2 ft
Main Spans: 2 at 4 m = 13.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 9.1 m = 29.9 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [02015]: Livingston County [105], Illinois [17]
Owned by City or Municipal Highway Agency [04], DOT District: 3
E OF WABASH ST
Condition
Deck: Not Applicable [N]
Superstructure: Not Applicable [N]
Substructure: Not Applicable [N]
Loading
Design: MS 18 / HS 20 [5]
Operating: 44.1 metric ton = 48.5 tons (Unknown [D])
Inventory: 32.4 metric ton = 35.6 tons (Unknown [D])
Appraisal
Structural: Equal to present desirable criteria [8]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Superior to present desirable criteria [9]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: September 2017 [0917] and Frequency: 48
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 25 (2019) and Trucks: 0%
Future ADT: 25 (In 2032 )
ILL 47/FAP 326 over VERMILION RIVER (Route: 47)
Num:53202800000000x
Open: no restriction [A]
Built: 1993, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Culvert [19]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Not applicable (applies only to structures with no deck) [N]
Bridge Dimensions
Length: 7 m = 23.0 ft
Main Spans: 2 at 3 m = 9.8 ft
Approach Spans: 0
Skew: 18
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 9.1 m = 29.9 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [02015]: Livingston County [105], Illinois [17]
Owned by State Highway Agency [01], DOT District: 3
.07 M S OF US 24
Condition
Deck: Not Applicable [N]
Superstructure: Not Applicable [N]
Substructure: Not Applicable [N]
Loading
Design: MS 18 / HS 20 [5]
Operating: 81 metric ton = 89.1 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 48.6 metric ton = 53.5 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: February 2018 [0218] and Frequency: 48
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 3600 (2019) and Trucks: 28%
Future ADT: 2839 (In 2032 )
OAK ST over S.FK VERMIION RIVER (Route: 0)
Num:53680200000000x
Open: no restriction [A]
Built: 1982, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.7 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Culvert [19]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 7.9 m = 25.9 ft
Main Spans: 2 at 3.7 m = 12.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.7 m = 25.3 ft (2 Lanes) and Out-To-Out: 7.9 m = 25.9 ft for a 6.4 m = 21.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [02015]: Livingston County [105], Illinois [17]
Owned by City or Municipal Highway Agency [04], DOT District: 3
OAK ST IN FORREST
Condition
Deck: Not Applicable [N]
Superstructure: Not Applicable [N]
Substructure: Not Applicable [N]
Loading
Design: MS 18 / HS 20 [5]
Operating: 44.4 metric ton = 48.8 tons (Unknown [D])
Inventory: 32.4 metric ton = 35.6 tons (Unknown [D])
Appraisal
Structural: Equal to present desirable criteria [8]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: September 2017 [0917] and Frequency: 48
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 175 (2019) and Trucks: 11%
Future ADT: 127 (In 2032 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact

Divider