Bridge Type
Main Span(s): Steel [3] Suspension [13]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Precast Panels [2] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 1519.7 m = 4986.1 ft
Main Spans: 3 at 1066.8 m = 3500.2 ft
Approach Spans: 8
Skew: 0
Width, Roadway: 21.9 m = 71.9 ft (6 Lanes) and Out-To-Out: 31.7 m = 104.0 ft for a 27.4 m = 89.9 ft approaching roadway.
Vertical Clearance: 4.44 m = 14.6 ft and Navigational Clearance: 64.9 m = 212.9 ft
Location
Fort Lee [24420]: Bergen County [003], New Jersey [34]
Owned by Local Toll Authority [32], DOT District: 1
I-95 over Hudson River LL
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design:
Operating: 63.5 metric ton = 69.9 tons (Load Factor(LF) [1])
Inventory: 38.1 metric ton = 41.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: September 1999 [999] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 1 km = 0.6 mi
Traffic
ADT: 282398 (2019) and Trucks: 10%
Future ADT: 344579 (In 2039
)