HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 5


BROADWAY over KILL BROOK: AQUEDUCT (Route: 0)
Num:2225180x
Open: no restriction [A]
Built: 1861, Reconstructed: N/A [0000]
Historic: Bridge is eligible for the NRHP. [2]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Masonry [8] Arch - Deck [11]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 26.8 m = 87.9 ft
Main Spans: 1 at 20.1 m = 65.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 6.4 m = 21.0 ft (2 Lanes) and Out-To-Out: 8.4 m = 27.6 ft for a 6.7 m = 22.0 ft approaching roadway.
Vertical Clearance: 3.75 m = 12.3 ft and Navigational Clearance: 0 = N/A
Location
Ossining [55530]: Westchester County [119], New York [36]
Owned by Town or Township Highway Agency [03], DOT District: 87
IN OSSINING
Condition
Deck: Not Applicable [N]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design:
Operating: 44.1 metric ton = 48.5 tons ()
Inventory: 17.2 metric ton = 18.9 tons ()
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations (including piles) on dry land well above flood water elevations. [9]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 1122 (2014) and Trucks: 1%
Future ADT: 1571 (In 2034 )
BRANDRETH STREET over KILL BROOK (Route: 0)
Num:2225190x
Open: no restriction [A]
Built: 1920, Reconstructed: 1988
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0 Miles (0.1 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 24.7 m = 81.0 ft
Main Spans: 1 at 24.3 m = 79.7 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 8.4 m = 27.6 ft (2 Lanes) and Out-To-Out: 11.3 m = 37.1 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Ossining [55530]: Westchester County [119], New York [36]
Owned by Town or Township Highway Agency [03], DOT District: 87
IN OSSINING
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 89.8 metric ton = 98.8 tons (Load Factor(LF) [1])
Inventory: 53.5 metric ton = 58.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 2705 (2015) and Trucks: 5%
Future ADT: 3787 (In 2035 )
RTE 9 over SING SING CREEK (Route: 9)
Num:1004950x
Open: no restriction [A]
Built: 1983, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.3 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Culvert [19]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 8.5 m = 27.9 ft
Main Spans: 2 at 3.6 m = 11.8 ft
Approach Spans: 0
Skew: 45
Width, Roadway: 13.4 m = 44.0 ft (4 Lanes) and Out-To-Out: 16.2 m = 53.2 ft for a 14.6 m = 47.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Ossining [55530]: Westchester County [119], New York [36]
Owned by State Highway Agency [01], DOT District: 87
0.2 MI N JCT RTS 9 & 133
Condition
Deck: Not Applicable [N]
Superstructure: Not Applicable [N]
Substructure: Not Applicable [N]
Loading
Design: MS 18 / HS 20 [5]
Operating: 75.1 metric ton = 82.6 tons ()
Inventory: 32.7 metric ton = 36.0 tons ()
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 15685 (2018) and Trucks: 4%
Future ADT: 15758 (In 2039 )
CENTRAL AVENUE over SING SING CREEK (Route: 0)
Num:2271220x
Open: no restriction [A]
Built: 1930, Reconstructed: N/A [0000]
Historic: Historical significance is not determinable at this time. [4]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Masonry [8] Arch - Deck [11]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface:
Bridge Dimensions
Length: 7.9 m = 25.9 ft
Main Spans: 1 at 7.6 m = 24.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 8.3 m = 27.2 ft (2 Lanes) and Out-To-Out: 13.2 m = 43.3 ft for a 8.3 m = 27.2 ft approaching roadway.
Vertical Clearance: 32.68 m = 107.2 ft and Navigational Clearance: 0 = N/A
Location
Ossining [55530]: Westchester County [119], New York [36]
Owned by Town or Township Highway Agency [03], DOT District: 87
0.3 mi SW Highland Avenue
Condition
Deck: Not Applicable [N]
Superstructure: Satisfactory [6]
Substructure: Fair [5]
Loading
Design:
Operating: 70.5 metric ton = 77.6 tons ()
Inventory: 18.9 metric ton = 20.8 tons ()
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: December 2020 [1220] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 823 (2019) and Trucks: 12%
Future ADT: 1152 (In 2039 )
WESTERLY ROAD over WESTERLY ROAD WAY: MNRR (Route: 0)
Num:7712790x
Open: no restriction [A]
Built: 1913, Reconstructed: 1990
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 157.3 m = 516.1 ft
Main Spans: 5 at 32.9 m = 107.9 ft
Approach Spans: 6
Skew: 0
Width, Roadway: 7.9 m = 25.9 ft (2 Lanes) and Out-To-Out: 9.6 m = 31.5 ft for a 7.9 m = 25.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Ossining [55530]: Westchester County [119], New York [36]
Owned by Town or Township Highway Agency [03], DOT District: 87
IN OSSINING
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Poor [4]
Loading
Design: MS 18 / HS 20 [5]
Operating: 34.5 metric ton = 38.0 tons (Load Factor(LF) [1])
Inventory: 20.9 metric ton = 23.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Basically intolerable requiring high priority of corrrective action [3]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 901 (2016) and Trucks: 7%
Future ADT: 1114 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider