BridgeSeek

Nearby Bridges in NBI 2021: 5


RTE I684 over MUSCOOT RESERVIOR (Route: 684)
Num:1053169x
Open: no restriction [A]
Built: 1966, Reconstructed: 1993
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Steel [3] Girder and floorbeam system [03]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 31.4 m = 103.0 ft
Main Spans: 1 at 29.8 m = 97.8 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 54.3 m = 178.2 ft (9 Lanes) and Out-To-Out: 59.1 m = 193.9 ft for a 54.3 m = 178.2 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Bedford [05320]: Westchester County [119], New York [36]
Owned by State Highway Agency [01], DOT District: 87
0.7MI N JCT RTS I684+SMRP
Condition
Deck: Fair [5]
Superstructure: Satisfactory [6]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 54 metric ton = 59.4 tons (Load Factor(LF) [1])
Inventory: 32.4 metric ton = 35.6 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 89385 (2019) and Trucks: 7%
Future ADT: 151364 (In 2039 )
RTE 35 over 684I684I87011178: RTE I6 (Route: 35)
Num:1053179x
Open: no restriction [A]
Built: 1966, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 64.3 m = 211.0 ft
Main Spans: 2 at 31.7 m = 104.0 ft
Approach Spans: 0
Skew: 55
Width, Roadway: 25.5 m = 83.7 ft (6 Lanes) and Out-To-Out: 26.5 m = 86.9 ft for a 24.4 m = 80.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Bedford [05320]: Westchester County [119], New York [36]
Owned by State Highway Agency [01], DOT District: 87
JCT RTS I684+35
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Poor [4]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 55.3 metric ton = 60.8 tons (Allowable Stress(AS) [2])
Inventory: 28.1 metric ton = 30.9 tons (Allowable Stress(AS) [2])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 23500 (2017) and Trucks: 6%
Future ADT: 23610 (In 2039 )
RTE 35 over MNRR HA LINE (Route: 35)
Num:1053319x
Open: no restriction [A]
Built: 1967, Reconstructed: 1993
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 18 m = 59.1 ft
Main Spans: 1 at 16.8 m = 55.1 ft
Approach Spans: 0
Skew: 25
Width, Roadway: 30.2 m = 99.1 ft (6 Lanes) and Out-To-Out: 31.1 m = 102.0 ft for a 29.3 m = 96.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Bedford [05320]: Westchester County [119], New York [36]
Owned by State Highway Agency [01], DOT District: 87
.1 MI W JCT SH 35 + I684
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 97.2 metric ton = 106.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 79.7 metric ton = 87.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: September 2020 [0920] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 1.1 km = 0.7 mi
Traffic
ADT: 23500 (2017) and Trucks: 6%
Future ADT: 23610 (In 2039 )
RTE 35 over MUSCOOT RESERVOIR (Route: 35)
Num:1053329x
Open: no restriction [A]
Built: 1968, Reconstructed: 1993
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 67.4 m = 221.1 ft
Main Spans: 2 at 32.6 m = 107.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 26.3 m = 86.3 ft (6 Lanes) and Out-To-Out: 27.2 m = 89.2 ft for a 25.3 m = 83.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Bedford [05320]: Westchester County [119], New York [36]
Owned by State Highway Agency [01], DOT District: 87
0.2 MI W JCT RTS 35+I684
Condition
Deck: Good [7]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 43.5 metric ton = 47.9 tons (Load Factor(LF) [1])
Inventory: 26.3 metric ton = 28.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 23500 (2017) and Trucks: 6%
Future ADT: 23610 (In 2039 )
JAY STREET over 684I684I87011175: ACCESS (Route: 0)
Num:1053150x
Open: no restriction [A]
Built: 1968, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 158.5 m = 520.0 ft
Main Spans: 5 at 35.6 m = 116.8 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.8 m = 25.6 ft (2 Lanes) and Out-To-Out: 10 m = 32.8 ft for a 7.6 m = 24.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Bedford [05320]: Westchester County [119], New York [36]
Owned by State Highway Agency [01], DOT District: 87
0.6MI N JCT RTS I684+SMRP
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 93.4 metric ton = 102.7 tons (Load Factor(LF) [1])
Inventory: 56.2 metric ton = 61.8 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 5298 (2015) and Trucks: 4%
Future ADT: 6436 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.