Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 25.9 m = 85.0 ft
Main Spans: 1 at 24.7 m = 81.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 6.1 m = 20.0 ft (2 Lanes) and Out-To-Out: 6.1 m = 20.0 ft for a 4.9 m = 16.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Washington [81200]: Defiance County [039], Ohio [39]
Owned by County Highway Agency [02], DOT District: 1
0.3 E OF MULLIGANS BLUFF
Condition
Deck: Very Good [8]
Superstructure: Very Good [8]
Substructure: Satisfactory [6]
Loading
Design: HL93 [A]
Operating: 45.4 metric ton = 49.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 32.4 metric ton = 35.6 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Basically intolerable requiring high priority of corrrective action [3] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: November 2020 [1120] and Frequency: 12
Future Work
Work Needed:
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 27 (2015) and Trucks: 7%
Future ADT: 37 (In 2038
)