HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 1


Columbus Ave CR120 over Pipe Creek (Route: 0)
Num:2231175x
Open: no restriction [A]
Built: 2020, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 25.3 m = 83.0 ft
Main Spans: 1 at 24.4 m = 80.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 15.9 m = 52.2 ft (3 Lanes) and Out-To-Out: 21.1 m = 69.2 ft for a 15.9 m = 52.2 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Perkins [61714]: Erie County [043], Ohio [39]
Owned by County Highway Agency [02], DOT District: 3
Columbus Ave-Pipe Cr-P209
Condition
Deck: Excellent [9]
Superstructure: Excellent [9]
Substructure: Excellent [9]
Loading
Design: HL93 [A]
Operating: 74.5 metric ton = 82.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 45.4 metric ton = 49.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Superior to present desirable criteria [9]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Superior to present desirable criteria [9]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: November 2020 [1120] and Frequency: 12
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 10500 (2020) and Trucks: 10%
Future ADT: 11500 (In 2040 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.