HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 5


COUNTY ROAD 20 over NORFOLK SOUTHERN (Route: 0)
Num:3349370x
Open: no restriction [A]
Built: 1966, Reconstructed: 1999
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 54.9 m = 180.1 ft
Main Spans: 3 at 21.9 m = 71.9 ft
Approach Spans: 0
Skew: 19
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 10.1 m = 33.1 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Kirkwood [39837]: Broome County [007], New York [36]
Owned by County Highway Agency [02], DOT District: 91
.2 MILE WEST OF KIRKWOOD
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 99.9 metric ton = 109.9 tons (Load Factor(LF) [1])
Inventory: 61.7 metric ton = 67.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: September 1999 [999] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.8 km = 0.5 mi
Traffic
ADT: 7384 (2018) and Trucks: 15%
Future ADT: 8970 (In 2039 )
CONKLIN-KIRKWOOD C over RTE 11 (Route: 0)
Num:1008070x
Open: no restriction [A]
Built: 1964, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 45.4 m = 149.0 ft
Main Spans: 3 at 14.9 m = 48.9 ft
Approach Spans: 0
Skew: 10
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 10.1 m = 33.1 ft for a 13.4 m = 44.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Kirkwood [39837]: Broome County [007], New York [36]
Owned by State Highway Agency [01], DOT District: 91
JCT US 11 & I81 - EXIT 1
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 79.8 metric ton = 87.8 tons (Load Factor(LF) [1])
Inventory: 47.2 metric ton = 51.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: September 2020 [0920] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 1.2 km = 0.7 mi
Traffic
ADT: 7384 (2018) and Trucks: 15%
Future ADT: 8970 (In 2039 )
COUNTY ROAD 20 over CR 209 MAIN STREET (Route: 0)
Num:3349360x
Open: no restriction [A]
Built: 1966, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 44.2 m = 145.0 ft
Main Spans: 3 at 19.5 m = 64.0 ft
Approach Spans: 0
Skew: 27
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 10.1 m = 33.1 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Kirkwood [39837]: Broome County [007], New York [36]
Owned by County Highway Agency [02], DOT District: 91
HAMLET OF KIRKWOOD
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 78 metric ton = 85.8 tons (Load Factor(LF) [1])
Inventory: 46.3 metric ton = 50.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: May 1999 [599] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.8 km = 0.5 mi
Traffic
ADT: 7384 (2018) and Trucks: 15%
Future ADT: 8970 (In 2039 )
RTE I81 over CEDARHURST ROAD (Route: 81)
Num:1031101x
Open: no restriction [A]
Built: 1960, Reconstructed: 2003
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 43.3 m = 142.1 ft
Main Spans: 3 at 14.9 m = 48.9 ft
Approach Spans: 0
Skew: 19
Width, Roadway: 11.9 m = 39.0 ft (2 Lanes) and Out-To-Out: 12.8 m = 42.0 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Kirkwood [39837]: Broome County [007], New York [36]
Owned by State Highway Agency [01], DOT District: 91
EXIT 1 RTE I-81
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 99.9 metric ton = 109.9 tons (Load Factor(LF) [1])
Inventory: 60.8 metric ton = 66.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 14451 (2010) and Trucks: 33%
Future ADT: 0 (In 2030 )
RTE I81 over CEDARHURST ROAD (Route: 81)
Num:1031102x
Open: no restriction [A]
Built: 1960, Reconstructed: 2003
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 46.9 m = 153.9 ft
Main Spans: 3 at 15.2 m = 49.9 ft
Approach Spans: 0
Skew: 19
Width, Roadway: 11.9 m = 39.0 ft (2 Lanes) and Out-To-Out: 12.8 m = 42.0 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Kirkwood [39837]: Broome County [007], New York [36]
Owned by State Highway Agency [01], DOT District: 91
EXIT 1 RTE I-81
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 98 metric ton = 107.8 tons (Load Factor(LF) [1])
Inventory: 58.1 metric ton = 63.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 12673 (2019) and Trucks: 40%
Future ADT: 16669 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.