Bridge Type
Main Span(s): Masonry [8] Arch - Deck [11]
Approach Span(s): Other [00]
Deck: Not applicable [N] with Wearing Surface: Not applicable (applies only to structures with no deck) [N]
Bridge Dimensions
Length: 8.5 m = 27.9 ft
Main Spans: 1 at 6.7 m = 22.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 8.9 m = 29.2 ft (2 Lanes) and Out-To-Out: 13.1 m = 43.0 ft for a 8.8 m = 28.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Brockton [09000]: Plymouth County [023], Massachusetts [25]
Owned by State Highway Agency [01], DOT District: 5
0.75 M N OF GROVE ST
Condition
Deck: Not Applicable [N]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design:
Operating: 99.9 metric ton = 109.9 tons (No rating analysis or evaluation performed [5])
Inventory: 41 metric ton = 45.1 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge is scour critical; bridge foundations determined to be unstable. [3]
Inspections
Date: January 2020 [0120] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge or other major structure without deck rehabilitation or replacement [33]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 8642 (2020) and Trucks: 7%
Future ADT: 28427 (In 2033
)