Bridge Type
Main Span(s): Steel [3] Truss - Thru [10]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 227.1 m = 745.1 ft
Main Spans: 3 at 74.6 m = 244.8 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 10 m = 32.8 ft for a 14.6 m = 47.9 ft approaching roadway.
Vertical Clearance: 4.52 m = 14.8 ft and Navigational Clearance: 0 = N/A
Location
Vestal [77255]: Broome County [007], New York [36]
Owned by County Highway Agency [02], DOT District: 91
HAMLET OF VESTAL
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 45.4 metric ton = 49.9 tons (Load Factor(LF) [1])
Inventory: 27.2 metric ton = 29.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: Somewhat better than minimum adequacy to tolerate being left in place as is [5] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: November 2020 [1120] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 16302 (2015) and Trucks: 2%
Future ADT: 19803 (In 2039
)