Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 15.5 m = 50.9 ft
Main Spans: 1 at 14.5 m = 47.6 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 15.9 m = 52.2 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Brimfield [08470]: Hampden County [013], Massachusetts [25]
Owned by State Highway Agency [01], DOT District: 2
0.1 MI E OF ST 19
Condition
Deck: Fair [5]
Superstructure: Satisfactory [6]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 45.6 metric ton = 50.2 tons (Load Factor(LF) [1])
Inventory: 27.3 metric ton = 30.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: March 2020 [0320] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 11897 (2018) and Trucks: 7%
Future ADT: 14296 (In 2033
)