Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 59.7 m = 195.9 ft
Main Spans: 2 at 33.5 m = 109.9 ft
Approach Spans: 0
Skew: 15
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 9.5 m = 31.2 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Cameron [11880]: Steuben County [101], New York [36]
Owned by County Highway Agency [02], DOT District: 64
.7 MILE NW OF CAMERON
Condition
Deck: Excellent [9]
Superstructure: Excellent [9]
Substructure: Excellent [9]
Loading
Design: HL93 [A]
Operating: 99.9 metric ton = 109.9 tons (Load Factor(LF) [1])
Inventory: 65.3 metric ton = 71.8 tons (Load Factor(LF) [1])
Appraisal
Structural: Superior to present desirable criteria [9]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4]
Inspections
Date: December 2020 [1220] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 2.4 km = 1.5 mi
Traffic
ADT: 408 (2017) and Trucks: 8%
Future ADT: 425 (In 2039
)