Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 136 m = 446.2 ft
Main Spans: 3 at 52 m = 170.6 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 13.2 m = 43.3 ft (2 Lanes) and Out-To-Out: 14 m = 45.9 ft for a 13.2 m = 43.3 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Josephine County [033], Oregon [41]
Owned by State Highway Agency [01], DOT District: 8
00.3 S MURPHY POST OFFICE
Condition
Deck: Satisfactory [6]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 41.8 metric ton = 46.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 32.1 metric ton = 35.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: October 1999 [1099] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 5.1 km = 3.2 mi
Traffic
ADT: 6200 (2018) and Trucks: 12%
Future ADT: 7400 (In 2038
)