Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 40.2 m = 131.9 ft
Main Spans: 1 at 39.6 m = 129.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 12.6 m = 41.3 ft (2 Lanes) and Out-To-Out: 13.6 m = 44.6 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Ulysses [75990]: Tompkins County [109], New York [36]
Owned by State Highway Agency [01], DOT District: 36
2.3 MI SE SENECA CO LINE
Condition
Deck: Good [7]
Superstructure: Very Good [8]
Substructure: Good [7]
Loading
Design: MS 22.5 / HS 25 or greater [9]
Operating: 68.9 metric ton = 75.8 tons (Load Factor(LF) [1])
Inventory: 42.6 metric ton = 46.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present minimum criteria [6] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.4 km = 0.2 mi
Traffic
ADT: 9448 (2018) and Trucks: 6%
Future ADT: 9506 (In 2039
)