SALMON STREET EB over MERRIMACK R:PAR:RD:RAMP (Route: 0)
Num:16101070007200x
Open: no restriction [A]
Built: 1970, Reconstructed: 1999
Historic: Bridge is possibly eligible for the NRHP. [3]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.1 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 311.8 m = 1023.0 ft
Main Spans: 4 at 51.5 m = 169.0 ft
Approach Spans: 4
Skew: 20
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 10.3 m = 33.8 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Manchester [45140]: Hillsborough County [011], New Hampshire [33]
Owned by City or Municipal Highway Agency [04], DOT District: 5
0.3MI W OF JCT RT 3
Condition
Deck: Poor [4]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 52.3 metric ton = 57.5 tons (Load Factor(LF) [1])
Inventory: 31.4 metric ton = 34.5 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: September 2020 [0920] and Frequency: 16
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 1.1 km = 0.7 mi
Traffic
ADT: 11821 (2018) and Trucks: 5%
Future ADT: 17495 (In 2041 )
SALMON STREET WB over MERRIMACK RIVER:PAR:RD (Route: 0)
Num:16101060007200x
Open: no restriction [A]
Built: 1970, Reconstructed: 1999
Historic: Bridge is possibly eligible for the NRHP. [3]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 261.5 m = 858.0 ft
Main Spans: 4 at 50.3 m = 165.0 ft
Approach Spans: 3
Skew: 20
Width, Roadway: 8.5 m = 27.9 ft (2 Lanes) and Out-To-Out: 11.3 m = 37.1 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Manchester [45140]: Hillsborough County [011], New Hampshire [33]
Owned by City or Municipal Highway Agency [04], DOT District: 5
.3MI W JCT US 3
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 74.1 metric ton = 81.5 tons (Load Factor(LF) [1])
Inventory: 44.5 metric ton = 49.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: September 2020 [0920] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 1.1 km = 0.7 mi
Traffic
ADT: 23318 (2018) and Trucks: 5%
Future ADT: 34510 (In 2041 )
RAMP E(CAMP ST) over PAR (Route: 0)
Num:16101070007100x
Open: no restriction [A]
Built: 1970, Reconstructed: N/A [0000]
Historic: Bridge is possibly eligible for the NRHP. [3]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 132.9 m = 436.0 ft
Main Spans: 6 at 21.3 m = 69.9 ft
Approach Spans: 0
Skew: 99
Width, Roadway: 6.7 m = 22.0 ft (1 Lanes) and Out-To-Out: 8.5 m = 27.9 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Manchester [45140]: Hillsborough County [011], New Hampshire [33]
Owned by City or Municipal Highway Agency [04], DOT District: 5
0.3 MI W JCT US 3
Condition
Deck: Fair [5]
Superstructure: Good [7]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 85.1 metric ton = 93.6 tons (Load Factor(LF) [1])
Inventory: 51.1 metric ton = 56.2 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 1.1 km = 0.7 mi
Traffic
ADT: 2000 (2019) and Trucks: 8%
Future ADT: 2960 (In 2041 )
SOUTH RAMP over I-293:FEE TPK (Route: 0)
Num:16101110006600x
Open: no restriction [A]
Built: 1957, Reconstructed: 1988
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 31.8 m = 104.3 ft
Main Spans: 2 at 15.9 m = 52.2 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 9.4 m = 30.8 ft (2 Lanes) and Out-To-Out: 11.4 m = 37.4 ft for a 9.8 m = 32.2 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Manchester [45140]: Hillsborough County [011], New Hampshire [33]
Owned by State Toll Authority [31], DOT District: 5
AT AMOSKEAG INTERCHANGE
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 53.3 metric ton = 58.6 tons (Load Factor(LF) [1])
Inventory: 32 metric ton = 35.2 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 2.6 km = 1.6 mi
Traffic
ADT: 14603 (2019) and Trucks: 4%
Future ADT: 21612 (In 2041 )
NORTH RAMP over I-293:FEE TPK (Route: 0)
Num:16101070006600x
Open: no restriction [A]
Built: 1957, Reconstructed: 1989
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 29.3 m = 96.1 ft
Main Spans: 2 at 14.4 m = 47.2 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 14.6 m = 47.9 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Manchester [45140]: Hillsborough County [011], New Hampshire [33]
Owned by State Toll Authority [31], DOT District: 5
.5MI FROM STARK LANE
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 57.2 metric ton = 62.9 tons (Load Factor(LF) [1])
Inventory: 34.3 metric ton = 37.7 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 2.6 km = 1.6 mi
Traffic
ADT: 16245 (2019) and Trucks: 8%
Future ADT: 24042 (In 2041 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.