Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 360.6 m = 1183.1 ft
Main Spans: 14 at 30.5 m = 100.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 21.9 m = 71.9 ft (6 Lanes) and Out-To-Out: 25.6 m = 84.0 ft for a 21.9 m = 71.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Wauwatosa [84675]: Milwaukee County [079], Wisconsin [55]
Owned by State Highway Agency [01], DOT District: 2
0.9 MI N JCT USH 18
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 47.4 metric ton = 52.1 tons (Load Factor(LF) [1])
Inventory: 27.5 metric ton = 30.3 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of corrrective action [3]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: June 2020 [0620] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 29200 (2019) and Trucks: 3%
Future ADT: 45650 (In 2039
)