Bridge Type
Main Span(s): Prestressed concrete [5] Slab [01]
Approach Span(s): Other [00]
Deck: Other [9] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 12.6 m = 41.3 ft
Main Spans: 1 at 12.5 m = 41.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 4.3 m = 14.1 ft (1 Lanes) and Out-To-Out: 4.9 m = 16.1 ft for a 3.7 m = 12.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Lane County [039], Oregon [41]
Owned by U.S. Forest Service [64], DOT District: 0
NO DATA ENTERED
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: M 18 / H 20 [4]
Operating: 62.7 metric ton = 69.0 tons (Allowable Stress(AS) [2])
Inventory: 36.3 metric ton = 39.9 tons (Allowable Stress(AS) [2])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: October 2020 [1020] and Frequency: 48
Future Work
Work Needed:
Bridge Detour: 15.8 km = 9.8 mi
Traffic
ADT: 2 (1998) and Trucks: 0%
Future ADT: 3 (In 2041
)