Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 46.6 m = 152.9 ft
Main Spans: 1 at 45.7 m = 149.9 ft
Approach Spans: 0
Skew: 11
Width, Roadway: 10.4 m = 34.1 ft (2 Lanes) and Out-To-Out: 12.5 m = 41.0 ft for a 10.4 m = 34.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Port Henry [59333]: Essex County [031], New York [36]
Owned by State Highway Agency [01], DOT District: 12
9N NORTH END PORT HENRY
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 88 metric ton = 96.8 tons (Load Factor(LF) [1])
Inventory: 33.6 metric ton = 37.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 1999 [799] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 1.6 km = 1.0 mi
Traffic
ADT: 3374 (2016) and Trucks: 8%
Future ADT: 3780 (In 2039
)