Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 39 m = 128.0 ft
Main Spans: 1 at 37.7 m = 123.7 ft
Approach Spans: 0
Skew: 25
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 14.5 m = 47.6 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Peru [57375]: Clinton County [019], New York [36]
Owned by State Highway Agency [01], DOT District: 71
0.1 MI S JCT RTS 22 + 22B
Condition
Deck: Satisfactory [6]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 66.2 metric ton = 72.8 tons (Load Factor(LF) [1])
Inventory: 39 metric ton = 42.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Meets minimum tolerable limits to be left in place as is [4] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: August 2020 [0820] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.8 km = 0.5 mi
Traffic
ADT: 7332 (2018) and Trucks: 9%
Future ADT: 7648 (In 2039
)