HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 14


CSAH 36 over BNSF RR (Route: 36)
Num:27A22x
Open: no restriction [A]
Built: 1996, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.1 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 64.6 m = 212.0 ft
Main Spans: 3 at 19.2 m = 63.0 ft
Approach Spans: 0
Skew: 53
Width, Roadway: 15.5 m = 50.9 ft (4 Lanes) and Out-To-Out: 24.3 m = 79.7 ft for a 15.5 m = 50.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by County Highway Agency [02], DOT District: 5
0.4 MI SE OF JCT TH 35W
Condition
Deck: Satisfactory [6]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 22.5 / HS 25 or greater [9]
Operating: 45.7 metric ton = 50.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 35.3 metric ton = 38.8 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: September 1999 [999] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 18200 (2014) and Trucks: 0%
Future ADT: 18200 (In 2034 )
MSAS 230 over BNSF RR (Route: 230)
Num:27A23x
Open: no restriction [A]
Built: 1996, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 49.2 m = 161.4 ft
Main Spans: 3 at 16.5 m = 54.1 ft
Approach Spans: 0
Skew: 37
Width, Roadway: 14.6 m = 47.9 ft (4 Lanes) and Out-To-Out: 25.5 m = 83.7 ft for a 14.6 m = 47.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by City or Municipal Highway Agency [04], DOT District: 5
0.1 MI N OF UNIV AVE
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 22.5 / HS 25 or greater [9]
Operating: 99.6 metric ton = 109.6 tons (Load Factor(LF) [1])
Inventory: 61.7 metric ton = 67.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: June 2020 [0620] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 2250 (2017) and Trucks: 0%
Future ADT: 2250 (In 2039 )
CSAH 37 over BNSF RR (Route: 37)
Num:27A24x
Open: no restriction [A]
Built: 1996, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 64.9 m = 212.9 ft
Main Spans: 3 at 21.5 m = 70.5 ft
Approach Spans: 0
Skew: 53
Width, Roadway: 14.9 m = 48.9 ft (3 Lanes) and Out-To-Out: 25.5 m = 83.7 ft for a 18.6 m = 61.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by County Highway Agency [02], DOT District: 5
0.4 MI SE OF JCT TH 35W
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 22.5 / HS 25 or greater [9]
Operating: 66.1 metric ton = 72.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 50.9 metric ton = 56.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: September 1999 [999] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 12500 (2017) and Trucks: 0%
Future ADT: 12500 (In 2039 )
CON 5937 over 2ND ST (Route: 5937)
Num:27414x
Open: no restriction [A]
Built: 2008, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 23.2 m = 76.1 ft
Main Spans: 1 at 23.2 m = 76.1 ft
Approach Spans: 0
Skew: 14
Width, Roadway: 12.5 m = 41.0 ft (2 Lanes) and Out-To-Out: 13.6 m = 44.6 ft for a 12.5 m = 41.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
1.2 MI NE JCT I94; I35W
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 79.1 metric ton = 87.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 61.2 metric ton = 67.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 77000 (2012) and Trucks: 3%
Future ADT: 77000 (In 2033 )
UNU 52 over I 35W (Route: 52)
Num:27883x
Open: no restriction [A]
Built: 1967, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 58.1 m = 190.6 ft
Main Spans: 4 at 18.6 m = 61.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 15.9 m = 52.2 ft (4 Lanes) and Out-To-Out: 21.4 m = 70.2 ft for a 15.9 m = 52.2 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
3.1 MI SW OF JCT TH 280
Condition
Deck: Poor [4]
Superstructure: Poor [4]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 66.9 metric ton = 73.6 tons (Load Factor(LF) [1])
Inventory: 40.2 metric ton = 44.2 tons (Load Factor(LF) [1])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 12
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 6941 (2019) and Trucks: 7%
Future ADT: 6900 (In 2039 )
MSAS 328 over MISS R; BNSF STS (Route: 328)
Num:2796x
Bridge closed to all traffic [K]
Built: 1929, Reconstructed: N/A [0000]
Historic: Bridge is on the NRHP. [1]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Arch - Deck [11]
Approach Span(s): Prestressed concrete [5] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 656.2 m = 2153.0 ft
Main Spans: 7 at 88.5 m = 290.4 ft
Approach Spans: 14
Skew: 0
Width, Roadway: 16.9 m = 55.4 ft (4 Lanes) and Out-To-Out: 20.8 m = 68.2 ft for a 23.2 m = 76.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 27.4 m = 89.9 ft
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by City or Municipal Highway Agency [04], DOT District: 5
0.3 MI N OF WASH AVE
Condition
Deck: Satisfactory [6]
Superstructure: Poor [4]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 33.7 metric ton = 37.1 tons (Load Factor(LF) [1])
Inventory: 20 metric ton = 22.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Better than present minimum criteria [7]
Waterway: Superior to present desirable criteria [9] and Countermeasures have been installed to mitigate an existing problem with scour. [7]
Inspections
Date: September 1999 [999] and Frequency: 12
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 8600 (2017) and Trucks: 0%
Future ADT: 8600 (In 2034 )
UNU 52 over I 35W (Route: 52)
Num:27882x
Open: no restriction [A]
Built: 1967, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 58.5 m = 191.9 ft
Main Spans: 4 at 18.1 m = 59.4 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 15.9 m = 52.2 ft (4 Lanes) and Out-To-Out: 21.4 m = 70.2 ft for a 15.9 m = 52.2 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
3.2 MI SW OF JCT TH 280
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 56 metric ton = 61.6 tons (Load Factor(LF) [1])
Inventory: 33.5 metric ton = 36.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 19300 (2017) and Trucks: 4%
Future ADT: 19300 (In 2039 )
I 35W over 2ND ST (Route: 35)
Num:27412x
Open: no restriction [A]
Built: 2008, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 23.7 m = 77.8 ft
Main Spans: 1 at 23.7 m = 77.8 ft
Approach Spans: 0
Skew: 14
Width, Roadway: 22.9 m = 75.1 ft (3 Lanes) and Out-To-Out: 23.9 m = 78.4 ft for a 22.9 m = 75.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
1.2 MI NE JCT I94; I35W
Condition
Deck: Very Good [8]
Superstructure: Very Good [8]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 80.4 metric ton = 88.4 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 59.6 metric ton = 65.6 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 76000 (2019) and Trucks: 4%
Future ADT: 84000 (In 2039 )
I 35W over 2ND ST (Route: 35)
Num:27411x
Open: no restriction [A]
Built: 2008, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 23.6 m = 77.4 ft
Main Spans: 1 at 23.6 m = 77.4 ft
Approach Spans: 0
Skew: 14
Width, Roadway: 29 m = 95.1 ft (5 Lanes) and Out-To-Out: 30 m = 98.4 ft for a 29 m = 95.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
1.2 MI NE JCT I94; I35W
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 81.6 metric ton = 89.8 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 55.4 metric ton = 60.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 84000 (2017) and Trucks: 3%
Future ADT: 84000 (In 2039 )
CSAH 122 over MISS. RIVER; STREETS (Route: 122)
Num:9360x
Open: no restriction [A]
Built: 1965, Reconstructed: 2000
Historic: Bridge is eligible for the NRHP. [2]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Girder and floorbeam system [03]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 344.7 m = 1131.0 ft
Main Spans: 5 at 96.1 m = 315.3 ft
Approach Spans: 1
Skew: 0
Width, Roadway: 17.7 m = 58.1 ft (4 Lanes) and Out-To-Out: 21.9 m = 71.9 ft for a 18.3 m = 60.0 ft approaching roadway.
Vertical Clearance: 5.3 m = 17.4 ft and Navigational Clearance: 16.5 m = 54.1 ft
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by County Highway Agency [02], DOT District: 5
0.6 MI E OF JCT TH 35W
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: HL93 [A]
Operating: 54.4 metric ton = 59.8 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 37.9 metric ton = 41.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Better than present minimum criteria [7]
Waterway: Equal to present desirable criteria [8] and Countermeasures have been installed to mitigate an existing problem with scour. [7]
Inspections
Date: August 1999 [899] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.5 km = 0.3 mi
Traffic
ADT: 6800 (2014) and Trucks: 2%
Future ADT: 6800 (In 2034 )
MSAS 419 over BNSF RR (Route: 419)
Num:27A21x
Open: no restriction [A]
Built: 1995, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 73.5 m = 241.2 ft
Main Spans: 3 at 21.8 m = 71.5 ft
Approach Spans: 0
Skew: 57
Width, Roadway: 13.4 m = 44.0 ft (3 Lanes) and Out-To-Out: 19 m = 62.3 ft for a 13.4 m = 44.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by City or Municipal Highway Agency [04], DOT District: 5
0.1 MI SE OF 15TH AVE SE
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 22.5 / HS 25 or greater [9]
Operating: 98.2 metric ton = 108.0 tons (Load Factor(LF) [1])
Inventory: 59 metric ton = 64.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 5474 (2017) and Trucks: 0%
Future ADT: 5474 (In 2034 )
I 35W over MISS R: W R PKWY: RD; RR (Route: 35)
Num:27410x
Open: no restriction [A]
Built: 2008, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Segmental box girder [21]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 374.2 m = 1227.8 ft
Main Spans: 4 at 151.9 m = 498.4 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 26.5 m = 86.9 ft (5 Lanes) and Out-To-Out: 27.5 m = 90.2 ft for a 26.5 m = 86.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 12.2 m = 40.0 ft
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
1.0 MI NE OF JCT TH 94
Condition
Deck: Good [7]
Superstructure: Very Good [8]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 45.4 metric ton = 49.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 35.6 metric ton = 39.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 1 km = 0.6 mi
Traffic
ADT: 76000 (2019) and Trucks: 4%
Future ADT: 84000 (In 2039 )
I 35W over MISS R: W R PKWY: RD; RR (Route: 35)
Num:27409x
Open: no restriction [A]
Built: 2008, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.7 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Segmental box girder [21]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 372 m = 1220.5 ft
Main Spans: 4 at 154 m = 505.3 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 27 m = 88.6 ft (5 Lanes) and Out-To-Out: 28 m = 91.9 ft for a 27 m = 88.6 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 12 m = 39.4 ft
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
1.0 MI NE OF JCT TH94
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 45.4 metric ton = 49.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 35.6 metric ton = 39.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Superior to present desirable criteria [9]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 1 km = 0.6 mi
Traffic
ADT: 84000 (2017) and Trucks: 4%
Future ADT: 84000 (In 2039 )
MSAS 231 over I 35W (Route: 231)
Num:27988x
Open: no restriction [A]
Built: 1969, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.7 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Low slump Concrete [4]
Bridge Dimensions
Length: 71.8 m = 235.6 ft
Main Spans: 2 at 36.8 m = 120.7 ft
Approach Spans: 0
Skew: 22
Width, Roadway: 13.4 m = 44.0 ft (2 Lanes) and Out-To-Out: 19.1 m = 62.7 ft for a 13.4 m = 44.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Minneapolis [43000]: Hennepin County [053], Minnesota [27]
Owned by State Highway Agency [01], DOT District: 5
2.8 MI SW OF JCT TH 280
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Fair [5]
Loading
Design: MS 18 / HS 20 [5]
Operating: 64.7 metric ton = 71.2 tons (Load Factor(LF) [1])
Inventory: 38.7 metric ton = 42.6 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: April 2020 [0420] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 6200 (2017) and Trucks: 0%
Future ADT: 6200 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact