HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 3


LRD 290TH AVENUE over MUD CREEK (Route: 0)
Num:B09016300000000x
Open: no restriction [A]
Built: 1991, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 12.7 m = 41.7 ft
Main Spans: 1 at 12.2 m = 40.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.3 m = 24.0 ft (2 Lanes) and Out-To-Out: 7.9 m = 25.9 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Sampson [71275]: Chippewa County [017], Wisconsin [55]
Owned by Town or Township Highway Agency [03], DOT District: 6
0.1 M E 190TH STREET
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Very Good [8]
Loading
Design: MS 18 / HS 20 [5]
Operating: 70.2 metric ton = 77.2 tons (Load Factor(LF) [1])
Inventory: 42.1 metric ton = 46.3 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: October 2020 [1020] and Frequency: 48
Future Work
Work Needed:
Bridge Detour: 1.6 km = 1.0 mi
Traffic
ADT: 106 (2018) and Trucks: 0%
Future ADT: 116 (In 2039 )
CTH Y over NSP POWER CANAL (Route: 0)
Num:B09012200000000x
Open: no restriction [A]
Built: 1986, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.5 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete continuous [6] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 63.9 m = 209.7 ft
Main Spans: 2 at 31.5 m = 103.4 ft
Approach Spans: 0
Skew: 15
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 9.8 m = 32.2 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Anson [02175]: Chippewa County [017], Wisconsin [55]
Owned by County Highway Agency [02], DOT District: 6
0.2 M E STH 178
Condition
Deck: Fair [5]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 90 metric ton = 99.0 tons (Load Factor(LF) [1])
Inventory: 42.1 metric ton = 46.3 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 1060 (2018) and Trucks: 0%
Future ADT: 1166 (In 2039 )
CTH Y over CHIPPEWA RIVER 15 (Route: 0)
Num:B09012300000000x
Open: no restriction [A]
Built: 1986, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 233.5 m = 766.1 ft
Main Spans: 5 at 51.8 m = 170.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 9.8 m = 32.2 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Anson [02175]: Chippewa County [017], Wisconsin [55]
Owned by County Highway Agency [02], DOT District: 6
0.1 M E STH 178
Condition
Deck: Fair [5]
Superstructure: Fair [5]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 53.9 metric ton = 59.3 tons (Load Factor(LF) [1])
Inventory: 32.4 metric ton = 35.6 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Basically intolerable requiring high priority of corrrective action [3]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: October 2020 [1020] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 1060 (2018) and Trucks: 0%
Future ADT: 1166 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact

Divider