HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 6


W 6TH STREET over MILL CREEK (Route: 0)
Num:00464 000000059x
Posted for load [P]
Built: 1920, Reconstructed: 2001
Historic: Bridge is eligible for the NRHP. [2]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 38.7 m = 127.0 ft
Main Spans: 4 at 12.2 m = 40.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 6.2 m = 20.3 ft (2 Lanes) and Out-To-Out: 9.5 m = 31.2 ft for a 7.3 m = 24.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
City of the Dalles [13425]: Wasco County [065], Oregon [41]
Owned by City or Municipal Highway Agency [04], DOT District: 9
CITY OF THE DALLES
Condition
Deck: Satisfactory [6]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: M 13.5 / H 15 [2]
Operating: 10.4 metric ton = 11.4 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 8.1 metric ton = 8.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Basically intolerable requiring high priority of corrrective action [3]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: August 2020 [0820] and Frequency: 12
Future Work
Work Needed: Widening of existing bridge or other major structure without deck rehabilitation or replacement [33]
Bridge Detour: 0.1 km = 0.1 mi
Traffic
ADT: 15627 (2020) and Trucks: 10%
Future ADT: 22842 (In 2025 )
I-84 (HWY 002) EB over UPRR (Route: 84)
Num:08603 002 08428x
Open: no restriction [A]
Built: 1964, Reconstructed: N/A [0000]
Historic: Historical significance is not determinable at this time. [4]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Concrete continuous [2] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 86.3 m = 283.2 ft
Main Spans: 1 at 34.7 m = 113.9 ft
Approach Spans: 5
Skew: 0
Width, Roadway: 9.8 m = 32.2 ft (2 Lanes) and Out-To-Out: 10.5 m = 34.5 ft for a 11.6 m = 38.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
City of the Dalles [13425]: Wasco County [065], Oregon [41]
Owned by State Highway Agency [01], DOT District: 9
IN THE DALLES
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 37.3 metric ton = 41.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 28.8 metric ton = 31.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: June 1999 [699] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 12650 (2018) and Trucks: 25%
Future ADT: 17650 (In 2038 )
I-84 (HWY 002) WB over UPRR (Route: 84)
Num:08603W002 08428x
Open: no restriction [A]
Built: 1964, Reconstructed: N/A [0000]
Historic: Historical significance is not determinable at this time. [4]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Concrete continuous [2] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 94.2 m = 309.1 ft
Main Spans: 1 at 38.4 m = 126.0 ft
Approach Spans: 5
Skew: 0
Width, Roadway: 9.3 m = 30.5 ft (2 Lanes) and Out-To-Out: 10 m = 32.8 ft for a 11.6 m = 38.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
City of the Dalles [13425]: Wasco County [065], Oregon [41]
Owned by State Highway Agency [01], DOT District: 9
IN THE DALLES
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 34 metric ton = 37.4 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 26.2 metric ton = 28.8 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Better than present minimum criteria [7]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: June 1999 [699] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 12650 (2018) and Trucks: 25%
Future ADT: 17650 (In 2038 )
I-84 (HWY 002) over HWY 292 O-XING (Route: 84)
Num:08775 002 08415x
Open: no restriction [A]
Built: 1964, Reconstructed: N/A [0000]
Historic: Historical significance is not determinable at this time. [4]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Steel continuous [4] Stringer/Multi-beam or girder [02]
Approach Span(s): Concrete continuous [2] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 138.4 m = 454.1 ft
Main Spans: 2 at 38.7 m = 127.0 ft
Approach Spans: 5
Skew: 0
Width, Roadway: 19 m = 62.3 ft (4 Lanes) and Out-To-Out: 20.5 m = 67.3 ft for a 11.6 m = 38.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
City of the Dalles [13425]: Wasco County [065], Oregon [41]
Owned by State Highway Agency [01], DOT District: 9
IN THE DALLES
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 18.1 metric ton = 19.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 13.9 metric ton = 15.3 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Basically intolerable requiring high priority of corrrective action [3]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present desirable criteria [8]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: June 1999 [699] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 25300 (2018) and Trucks: 25%
Future ADT: 35300 (In 2038 )
W 10TH STREET over MILL CREEK (Route: 0)
Num:16010 000 00320x
Open: no restriction [A]
Built: 1975, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.7 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Epoxy Overlay [5]
Bridge Dimensions
Length: 34.1 m = 111.9 ft
Main Spans: 1 at 33.5 m = 109.9 ft
Approach Spans: 0
Skew: 45
Width, Roadway: 13.4 m = 44.0 ft (2 Lanes) and Out-To-Out: 17.2 m = 56.4 ft for a 13.4 m = 44.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
City of the Dalles [13425]: Wasco County [065], Oregon [41]
Owned by City or Municipal Highway Agency [04], DOT District: 9
CITY OF THE DALLES
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 68.9 metric ton = 75.8 tons (Allowable Stress(AS) [2])
Inventory: 40.8 metric ton = 44.9 tons (Allowable Stress(AS) [2])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge is scour critical; bridge foundations determined to be unstable. [3]
Inspections
Date: August 2020 [0820] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 8665 (2020) and Trucks: 10%
Future ADT: 9415 (In 2025 )
W 9TH STREET over MILL CREEK (Route: 0)
Num:00463 365 00103x
Open: no restriction [A]
Built: 1987, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.5 Miles (0.7 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Epoxy Overlay [5]
Bridge Dimensions
Length: 30.2 m = 99.1 ft
Main Spans: 1 at 29.9 m = 98.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 13.4 m = 44.0 ft (2 Lanes) and Out-To-Out: 17.5 m = 57.4 ft for a 13.4 m = 44.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
City of the Dalles [13425]: Wasco County [065], Oregon [41]
Owned by City or Municipal Highway Agency [04], DOT District: 9
CITY OF THE DALLES
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Very Good [8]
Loading
Design: MS 22.5 / HS 25 or greater [9]
Operating: 64.4 metric ton = 70.8 tons (Allowable Stress(AS) [2])
Inventory: 39 metric ton = 42.9 tons (Allowable Stress(AS) [2])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4]
Inspections
Date: August 2020 [0820] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 2138 (2020) and Trucks: 10%
Future ADT: 2448 (In 2025 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.