OLD US 2 over BIG CEDAR (Route: 0)
Num:6870x
Open: no restriction [A]
Built: 1995, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 22.8 m = 74.8 ft
Main Spans: 1 at 21.9 m = 71.9 ft
Approach Spans: 0
Skew: 15
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 9.5 m = 31.2 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Spalding [75360]: Menominee County [109], Michigan [26]
Owned by County Highway Agency [02], DOT District: 1
0.25 MI N POWERS
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 63.8 metric ton = 70.2 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 38.2 metric ton = 42.0 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: June 1999 [699] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 100 (1991) and Trucks: 0%
Future ADT: 115 (In 2019 )
US-2 US-41 over BIG CEDAR RIVER (Route: 2)
Num:6796x
Open: no restriction [A]
Built: 1932, Reconstructed: 1987
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.2 Miles (0.3 Kilometers)

Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 13.7 m = 44.9 ft
Main Spans: 1 at 13.7 m = 44.9 ft
Approach Spans: 0
Skew: 20
Width, Roadway: 12.2 m = 40.0 ft (2 Lanes) and Out-To-Out: 15.9 m = 52.2 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Spaulding [75460]: Menominee County [109], Michigan [26]
Owned by State Highway Agency [01], DOT District: 1
0.6 MI E OF POWERS
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Fair [5]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 66.7 metric ton = 73.4 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Inventory: 40.2 metric ton = 44.2 tons (Load Factor (LF) rating reported by rating factor (RF) method using MS18 loading [6])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: August 1999 [899] and Frequency: 24
Future Work
Work Needed: Bridge deck replacement with only incidental widening. [37]
Bridge Detour: 0 km = 0.0 mi
Traffic
ADT: 6417 (2007) and Trucks: 8%
Future ADT: 7546 (In 2018 )
ROUTE 566 over BIG CEDAR RIVER (Route: 5557)
Num:6832x
Open: no restriction [A]
Built: 1985, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.3 Miles (0.4 Kilometers)

Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 17.3 m = 56.8 ft
Main Spans: 1 at 17.3 m = 56.8 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 9.5 m = 31.2 ft for a 7 m = 23.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Spaulding [75460]: Menominee County [109], Michigan [26]
Owned by County Highway Agency [02], DOT District: 1
IN SPALDING
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: MS 18 / HS 20 [5]
Operating: 57 metric ton = 62.7 tons (Allowable Stress(AS) [2])
Inventory: 34 metric ton = 37.4 tons (Allowable Stress(AS) [2])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Better than present minimum criteria [7]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: June 1999 [699] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.5 km = 0.3 mi
Traffic
ADT: 150 (0) and Trucks: 0%
Future ADT: 185 (In 2019 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.