HistoricBridges.org Menu: HistoricBridges.org Menu:



BridgeSeek

Nearby Bridges in NBI 2021: 4


US 195 over S FK PALOUSE RIVER (Route: 195)
Num:0001869A0000000x
Open: no restriction [A]
Built: 1934, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0 Miles (0 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 34.4 m = 112.9 ft
Main Spans: 2 at 17.1 m = 56.1 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 13.4 m = 44.0 ft (4 Lanes) and Out-To-Out: 17.2 m = 56.4 ft for a 17.1 m = 56.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Whitman County [075], Washington [53]
Owned by State Highway Agency [01], DOT District: 6
15.2 N JCT SR 270
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design: M 13.5 / H 15 [2]
Operating: 40.8 metric ton = 44.9 tons (Load Factor(LF) [1])
Inventory: 24.5 metric ton = 27.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 2018 [0718] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 9955 (2019) and Trucks: 11%
Future ADT: 11149 (In 2039 )
US 195 over SPRING FLAT CREEK (Route: 195)
Num:000000GR0000000x
Open: no restriction [A]
Built: 1920, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.1 Miles (0.2 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 11.3 m = 37.1 ft
Main Spans: 1 at 11.3 m = 37.1 ft
Approach Spans: 0
Skew: 53
Width, Roadway: 17.1 m = 56.1 ft (4 Lanes) and Out-To-Out: 24.4 m = 80.1 ft for a 17.1 m = 56.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Whitman County [075], Washington [53]
Owned by State Highway Agency [01], DOT District: 6
15.1 N JCT SR 270
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design:
Operating: 32.7 metric ton = 36.0 tons (Load Factor(LF) [1])
Inventory: 20 metric ton = 22.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 2018 [0718] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 1.3 km = 0.8 mi
Traffic
ADT: 9087 (2019) and Trucks: 12%
Future ADT: 10177 (In 2039 )
WALL STREET over SOUTH FORK PALOUSE RIVER (Route: 230)
Num:85208000000000x
Open: no restriction [A]
Built: 1965, Reconstructed: N/A [0000]
Historic: Historical significance is not determinable at this time. [4]

Google Streetview (If Available)

Rough Distance: 0.4 Miles (0.6 Kilometers)

Bridge Type
Main Span(s): Concrete [1] Tee beam [04]
Approach Span(s): Other [00]
Deck: Other [9] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 23.2 m = 76.1 ft
Main Spans: 1 at 22.6 m = 74.2 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 8.1 m = 26.6 ft (2 Lanes) and Out-To-Out: 9.7 m = 31.8 ft for a 10.4 m = 34.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Colfax [13785]: Whitman County [075], Washington [53]
Owned by City or Municipal Highway Agency [04], DOT District: 6
0.10 MI W SR 195
Condition
Deck: Satisfactory [6]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design:
Operating: 25.4 metric ton = 27.9 tons ()
Inventory: 15.4 metric ton = 16.9 tons ()
Appraisal
Structural: Meets minimum tolerable limits to be left in place as is [4]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: January 2021 [0121] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 200 (2020) and Trucks: 5%
Future ADT: 204 (In 2039 )
US 195 over S FK PALOUSE RIVER (Route: 195)
Num:000000BI0000000x
Open: no restriction [A]
Built: 1923, Reconstructed: N/A [0000]
Historic: Bridge is not eligible for the NRHP. [5]

Google Streetview (If Available)

Rough Distance: 0.5 Miles (0.8 Kilometers)

Bridge Type
Main Span(s): Concrete continuous [2] Tee beam [04]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 69.5 m = 228.0 ft
Main Spans: 2 at 34.7 m = 113.9 ft
Approach Spans: 0
Skew: 70
Width, Roadway: 17.1 m = 56.1 ft (4 Lanes) and Out-To-Out: 24.4 m = 80.1 ft for a 17.1 m = 56.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Whitman County [075], Washington [53]
Owned by State Highway Agency [01], DOT District: 6
0.3 N JCT SR 272
Condition
Deck: Satisfactory [6]
Superstructure: Poor [4]
Substructure: Satisfactory [6]
Loading
Design:
Operating: 24.5 metric ton = 27.0 tons (Load Factor(LF) [1])
Inventory: 14.5 metric ton = 16.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Basically intolerable requiring high priority of corrrective action [3]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 1.3 km = 0.8 mi
Traffic
ADT: 9894 (2019) and Trucks: 11%
Future ADT: 11081 (In 2039 )

Special Bridge Conditions Legend: R - Former location of relocated bridge. ! - At risk for demolition or destruction. X - Confirmed demolished or collapsed. S  - Dismantled and/or in storage. L -  Severe loss of historic integrity due to alteration.

Divider

Back

Top

Divider

About - Contact

Divider