Bridge Type
Main Span(s): Prestressed concrete [5] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Other [9] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 19.2 m = 63.0 ft
Main Spans: 1 at 18.6 m = 61.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 7.9 m = 25.9 ft (2 Lanes) and Out-To-Out: 8.5 m = 27.9 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Spokane County [063], Washington [53]
Owned by County Highway Agency [02], DOT District: 6
1.0 E CHENEY-SPOK
Condition
Deck: Satisfactory [6]
Superstructure: Good [7]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 54.4 metric ton = 59.8 tons (Load Factor(LF) [1])
Inventory: 32.7 metric ton = 36.0 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: August 2020 [0820] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 1.9 km = 1.2 mi
Traffic
ADT: 221 (2020) and Trucks: 16%
Future ADT: 318 (In 2042
)