Bridge Type
Main Span(s): Concrete continuous [2] Tee beam [04]
Approach Span(s): Concrete [1] Tee beam [04]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Latex Concrete or similar additive [3]
Bridge Dimensions
Length: 45.7 m = 149.9 ft
Main Spans: 3 at 24.7 m = 81.0 ft
Approach Spans: 2
Skew: 26
Width, Roadway: 12.8 m = 42.0 ft (2 Lanes) and Out-To-Out: 15.8 m = 51.8 ft for a 12.2 m = 40.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Spokane [67000]: Spokane County [063], Washington [53]
Owned by City or Municipal Highway Agency [04], DOT District: 6
01.06 NORTH SR195
Condition
Deck: Satisfactory [6]
Superstructure: Satisfactory [6]
Substructure: Satisfactory [6]
Loading
Design: M 13.5 / H 15 [2]
Operating: 51.7 metric ton = 56.9 tons (Load Factor(LF) [1])
Inventory: 30.8 metric ton = 33.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Equal to present minimum criteria [6]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Countermeasures have been installed to mitigate an existing problem with scour. [7]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Bridge deck rehabilitation with only incidental widening. [36]
Bridge Detour: 0.6 km = 0.4 mi
Traffic
ADT: 3100 (2016) and Trucks: 1%
Future ADT: 8500 (In 2039
)