Bridge Type
Main Span(s): Concrete continuous [2] Slab [01]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Epoxy Overlay [5]
Bridge Dimensions
Length: 33.8 m = 110.9 ft
Main Spans: 3 at 14.6 m = 47.9 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 6.1 m = 20.0 ft (2 Lanes) and Out-To-Out: 8.4 m = 27.6 ft for a 7.9 m = 25.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Cascade [13400]: Williamsburg city [830], Virginia [51]
Owned by City or Municipal Highway Agency [04], DOT District: 5
0.01 TO 5 0.28 TO 60
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Very Good [8]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 38.4 metric ton = 42.2 tons (Load and Resistance Factor(LRFR) [3])
Inventory: 29.6 metric ton = 32.6 tons (Load and Resistance Factor(LRFR) [3])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present minimum criteria [6]
Waterway: N/A [N] and Bridge not over waterway. [N]
Inspections
Date: May 2020 [0520] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 2146 (1992) and Trucks: 1%
Future ADT: 8500 (In 2027
)