Bridge Type
Main Span(s): Steel [3] Truss - Thru [10]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 39.9 m = 130.9 ft
Main Spans: 1 at 24.4 m = 80.1 ft
Approach Spans: 2
Skew: 0
Width, Roadway: 6 m = 19.7 ft (2 Lanes) and Out-To-Out: 6.2 m = 20.3 ft for a 7.9 m = 25.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Lincoln [28000]: Lancaster County [109], Nebraska [31]
Owned by Other State Agencies [21], DOT District: 1
38TH ST ON EAST CAMPUS
Condition
Deck: Good [7]
Superstructure: Fair [5]
Substructure: Fair [5]
Loading
Design:
Operating: 15 metric ton = 16.5 tons (Load Factor(LF) [1])
Inventory: 9 metric ton = 9.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Basically intolerable requiring high priority of corrrective action [3]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: March 2020 [0320] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 3 km = 1.9 mi
Traffic
ADT: 1200 (2003) and Trucks: 10%
Future ADT: 1740 (In 2033
)