Bridge Type
Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 11.9 m = 39.0 ft
Main Spans: 1 at 11.2 m = 36.7 ft
Approach Spans: 0
Skew: 15
Width, Roadway: 9.2 m = 30.2 ft (2 Lanes) and Out-To-Out: 12.3 m = 40.4 ft for a 8.5 m = 27.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
New Haven [52992]: Allen County [003], Indiana [18]
Owned by County Highway Agency [02], DOT District: 2
00.20 E OF GREEN ST
Condition
Deck: Good [7]
Superstructure: Fair [5]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 81.6 metric ton = 89.8 tons (Load Factor(LF) [1])
Inventory: 49 metric ton = 53.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: May 2020 [0520] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 1683 (2018) and Trucks: 5%
Future ADT: 2798 (In 2038
)