Bridge Type
Main Span(s): Steel [3] Arch - Deck [11]
Approach Span(s): Other [00]
Deck: Closed Grating [4] with Wearing Surface: Bituminous [6]
Bridge Dimensions
Length: 25.9 m = 85.0 ft
Main Spans: 1 at 25.7 m = 84.3 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 6.1 m = 20.0 ft (2 Lanes) and Out-To-Out: 9.7 m = 31.8 ft for a 6.1 m = 20.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
New Haven [52070]: New Haven County [009], Connecticut [09]
Owned by City or Municipal Highway Agency [04], DOT District: 3
AT JUNCT W FARNUM DRIVE
Condition
Deck: Good [7]
Superstructure: Satisfactory [6]
Substructure: Good [7]
Loading
Design: HL93 [A]
Operating: 44.7 metric ton = 49.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 34.3 metric ton = 37.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Equal to present minimum criteria [6]
Waterway: Better than present minimum criteria [7] and Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Inspections
Date: November 1999 [1199] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 0.2 km = 0.1 mi
Traffic
ADT: 1324 (2019) and Trucks: 4%
Future ADT: 1967 (In 2039
)