Bridge Type
Main Span(s): Prestressed concrete continuous [6] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 97.8 m = 320.9 ft
Main Spans: 4 at 25 m = 82.0 ft
Approach Spans: 0
Skew: 45
Width, Roadway: 11 m = 36.1 ft (2 Lanes) and Out-To-Out: 12.1 m = 39.7 ft for a 11 m = 36.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Lumber [45432]: Cameron County [023], Pennsylvania [42]
Owned by State Highway Agency [01], DOT District: 2
CAMERON
Condition
Deck: Good [7]
Superstructure: Good [7]
Substructure: Good [7]
Loading
Design: M 13.5 / H 15 [2]
Operating: 86.2 metric ton = 94.8 tons (Load Factor(LF) [1])
Inventory: 50.8 metric ton = 55.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Better than present minimum criteria [7]
Road Alignment: Better than present minimum criteria [7]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: May 2020 [0520] and Frequency: 24
Future Work
Work Needed:
Bridge Detour: 10.9 km = 6.8 mi
Traffic
ADT: 450 (2020) and Trucks: 19%
Future ADT: 691 (In 2040
)