Bridge Type
Main Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Approach Span(s): Steel [3] Stringer/Multi-beam or girder [02]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]
Bridge Dimensions
Length: 56.4 m = 185.0 ft
Main Spans: 1 at 41.1 m = 134.8 ft
Approach Spans: 1
Skew: 0
Width, Roadway: 4 m = 13.1 ft (1 Lanes) and Out-To-Out: 4.6 m = 15.1 ft for a 4 m = 13.1 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Hadley [31269]: Saratoga County [091], New York [36]
Owned by County Highway Agency [02], DOT District: 15
0.25MI SE OF HADLEY
Condition
Deck: Very Good [8]
Superstructure: Very Good [8]
Substructure: Satisfactory [6]
Loading
Design: MS 18 / HS 20 [5]
Operating: 99.9 metric ton = 109.9 tons (Load Factor(LF) [1])
Inventory: 59.9 metric ton = 65.9 tons (Load Factor(LF) [1])
Appraisal
Structural: Equal to present minimum criteria [6]
Deck Geometry: Basically intolerable requiring high priority of replacement [2]
Road Alignment: Meets minimum tolerable limits to be left in place as is [4]
Waterway: Superior to present desirable criteria [9] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: July 2020 [0720] and Frequency: 24
Future Work
Work Needed: Widening of existing bridge with deck rehabilitation or replacement. [34]
Bridge Detour: 0.9 km = 0.6 mi
Traffic
ADT: 981 (2018) and Trucks: 4%
Future ADT: 1373 (In 2038
)